Skip to content

PROJECT EXAMPLES

DIMENSION CARGO

Transformer: Approx. 11,2 x 3,9 x 4,5 m, Weight: approx. 305 t

VEHICLE TECHNOLOGY USES

  • 16-axle SPMT
  • 2 × 14-axle Schnabel bridges (G² I K 600) with temporarily added axle lines
  • 19-axle heavy-duty flatbed trailer
  • Hydraulic lifting and strand jacking systems (4 × 200 t)
  • Skidding systems for lateral load movements
  • Load distribution plates, steel beams and pedestals
  • Temporary bridge crossing systems
  • Multiple prime movers for push and pull operations on steep gradients

COMBINED HEAVY-LIFT TECHNIQUES FOR THE TRANSPORT OF A 305-TONNE TRANSFORMER

In December 2025, KAHL SCHWERLAST GmbH successfully executed a highly complex heavy-lift project to support the energy supply infrastructure in North Rhine-Westphalia. The project involved the transport and positioning of a 305-tonne power transformer destined for the Arpe substation. Due to the transformer’s exceptional dimensions, extreme weight and the challenging topographical and infrastructural conditions, the project placed the highest demands on planning, engineering and execution.

Special Challenges:

  • Transport and positioning of a 305-tonne power transformer
  • Combination of multiple heavy-lift techniques within an integrated overall concept
  • Lateral skidding out of the rail axis without crane operations
  • Deployment of SPMT, Schnabel bridge technology and heavy-duty flatbed transport
  • Negotiation of gradients exceeding 9% using push and pull vehicles
  • Temporary bridge crossing systems to protect existing infrastructure
  • Precise lateral positioning at the destination site
  • Highest safety and quality standards throughout all project phases

More

DIMENSION CARGO

Lower column section: approx. 22,0 × 4,7 × 5,0 m, approx. 78 t (L × W × H)
Upper column section: approx. 30,7 × 5,9 × 4,9 m, approx. 95 t (L × W × H)

VEHICLE TECHNOLOGY USES

  • Vessel bridge with 2 × 6-axle THP modules and 22 m longitudinal beams
  • 2 × 6-axle platform trailers with 9 m beams
  • Variably extendable vessel bridge (extension up to 31 m)
  • Pontoon transport across the River Rhine
  • Modular axle combinations for precise manoeuvring
  • Special bridge crossing systems for uniform load distribution
2025-BSK-Award-Platz-1-KS-weiss

SPECIAL SOLUTION FOR COLUMN TRANSPORTS AT THE WESSELING CHEMICAL PARK

Between February and May 2025, KAHL SCHWERLAST GmbH carried out an exceptionally demanding heavy transport project for Shell Deutschland GmbH to the Wesseling Chemical Park. Two large-scale column sections with lengths of up to 31 metres, heights of almost five metres and individual weights of up to 95 tonnes were transported. The objective was a safe, precise and on-time delivery without any structural modifications to the existing plant infrastructure.

Special Challenges:

  • Transport of two large-scale column sections for the chemical industry
  • Individual weights of up to 95 t with lengths of up to 31 m
  • Multimodal transport concept (road – pontoon – plant transport)
  • Extremely limited clearance heights within the plant site (max. 5,1 m)
  • Variably extendable vessel bridge to achieve minimal transport height
  • Precise, centimetre-accurate passage beneath pipe bridges
  • Execution without any structural modifications to Shell’s infrastructure
  • High safety standards and comprehensive risk analyses

More

DIMENSION CARGO

2 Transformatoren: Gewicht je Einheit: 334 t und
Abmessungen je Einheit: ca. 10,29 × 3,90 × 5,00 m

VEHICLE TECHNOLOGY USES

  • Floating crane (800 t)
  • Strand jacking systems at the Nuremberg plant
  • Vessel-mounted crane systems (single and tandem lifting)
  • Special block, barrier and chain systems for cargo securing
  • Shock recorders for monitoring mechanical loads
  • Engineering in accordance with MWS, DNV-ST-N001 and IMO requirements
2025-BSK-Award-Platz-3-KJL-weiss

INTERNATIONAL HEAVY CARGO PROJECT LOGISTICS: TRANSFORMER TRANSPORT FROM NUREMBERG TO DUBAI

At the end of 2024, KAHL & JANSEN GmbH carried out a highly complex international heavy cargo project involving the transport, transshipment and intermediate storage of two Siemens transformers, each weighing 334 tonnes, as well as 55 accessory crates, from Nuremberg via Antwerp to the port of Jebel Ali in Dubai. The project placed the highest demands on engineering, safety, coordination and international logistics expertise.

Special Challenges:

  • Transport of two transformers, each with an individual weight of 334 t
  • Multimodal project logistics (road – inland waterway – seagoing vessel)
  • International execution from Germany via Belgium to the United Arab Emirates
  • Deployment of an 800-tonne floating crane and complex single and tandem lifting concepts
  • Comprehensive cargo securing in accordance with DNV standards
  • Continuous involvement of a Marine Warranty Surveyor (MWS)
  • Ongoing adaptation and re-certification of method statements and lifting plans
  • Installation of shock recorders for continuous transport monitoring
  • Close coordination with international contractors and the end customer

More

DIMENSION CARGO

Building bridge 1: length approx. 27,5 m, weight approx. 42 t
Building bridge 2: length approx. 22,3 m, weight approx. 28 t

OVERALL TRANSPORT DIMENSION

  • Transport route: approx. 1,000 km (alternative route)
  • Internal transport width: up to 5,120 mm
  • Transport carried out predominantly as night transport
  • Installation carried out directly on the hospital premises

VEHICLE TECHNOLOGY USES

  • 65-tonne lifting beam bridge for torsion-free special transport
  • 5+3-axle low-bed combination with double extension beams
  • 450-tonne mobile crane (type LTM 1450)
  • Temporary crane base reinforcement with more than 400 support props
  • Police escort, road closures and traffic management measures
2025-BSK-Award-Platz-2-PS-weiss

HEAVY TRANSPORT OF LARGE-SCALE BUILDING BRIDGES FOR THE BERLIN-MARZAHN TRAUMA HOSPITAL

In December 2024, PIEPER Schwertransporte GmbH carried out a technically demanding heavy transport project for the Berlin-Marzahn Trauma Hospital. The project involved two large-scale steel-and-glass building bridges that will in future provide a weather-protected and barrier-free connection between the main building and the Neurology Clinic.

Special Challenges:

  • Transport of two large-scale steel-and-glass building bridges during ongoing hospital operations
  • Highly sensitive components up to 27,5 m in length and weighing up to 42 t
  • Development and implementation of an alternative route of approximately 1,000 km
  • First-time use of a 65-tonne lifting beam bridge to ensure torsion-free transport
  • Installation under extreme conditions (basement structure, helicopter flight path)
  • Precise lifting operations using a 450-tonne mobile crane
  • Close coordination with the hospital, authorities, emergency services and air rescue teams
  • Highest safety standards in a public and medical environment

More

DIMENSION CARGO

Steam tug: approx. 19,5 × 4,5 × 5,5 m, 55 t (L × W × H)

OVERALL TRANSPORT DIMENSION

  • Internal relocation within the Shipping Hall
  • Total relocation distance: approx. 23 m
    First stage: approx. 8 m
    Second stage: approx. 15 m
  • Additional bow rotation of approx. 12°

VEHICLE TECHNOLOGY USES

  • Specially designed steel support frame
  • Hydraulic jacking systems (lifting at 20 points)
  • Transport skids / sliding track system
  • Temporary shoring system to support the hall floor and basement ceiling
  • Continuous load and structural monitoring throughout all project phases
2025-BSK-Award-Platz-3-KJL-Montage-weiss

HEAVY LIFT ENGINEERING FOR THE PRESERVATION OF CULTURAL HERITAGE

As part of the comprehensive general refurbishment of the Deutsches Museum in Munich, KAHL & JANSEN was entrusted with an exceptional task: the internal relocation of the historic steam tug Renzo within the Shipping Hall. Built in 1931, the vessel weighs approximately 55 tonnes and is one of the largest and heaviest exhibits in the museum, forming a central element of the exhibition.

Special Challenges:

  • Internal heavy-load relocation of a historic exhibit without removing it from the building
  • Custom-designed support frame precisely adapted to the vessel’s hull contour and the hall geometry
  • Hydraulic lifting at 20 points to ensure torsion-free load absorption
  • Multi-stage relocation concept with intermediate positions and a 12° bow rotation
  • Operations carried out under the strictest safety and structural requirements (maximum floor load 5 t/m²)
  • Listed building environment with the highest demands on precision and damage prevention
  • All equipment and materials brought in exclusively by hand, without the use of cranes or forklifts

More

DIMENSION CARGO

Multiple rotor blades

  • Dimensions per rotor blade: 80 m length, 4.50 m diameter
  • Weight per rotor blade: approx. 25 t

VEHICLE TECHNOLOGY USES

  • Wing transport device FTV 850

 

EFFICIENT HEAVY CARGO LOGISTICS FOR MODERN WIND ENERGY PROJECTS

We are currently supporting a large-scale wind power project involving the transport of a large number of oversized rotor blades over a period of several months. We are using our proven FTV 850 blade transport device, which was specially developed for the safe and flexible transport of wind power components.

Customized work in the heavy-duty sector
The rotor blades to be transported are impressive in size: 80 meters long, 4.50 meters in diameter, and weighing around 25 tons each. Due to their size and shape, these components pose particular logistical challenges – both in terms of planning and transport.

With the FTV 850, the rotor blades can be precisely lifted, tilted, and adapted to the respective route conditions using hydraulic lifting and swiveling technology. This allows tight curves, height restrictions, and critical bottlenecks to be safely overcome – even in challenging terrain.

Project with vision
As the project is scheduled to run for several months, the rotor blades are being transported in stages and as required, in close coordination with construction progress, time windows, external partners, and the client. The FTV 850 not only enables technical flexibility, but also a high level of efficiency in execution.

With careful preparation, specialized technology, and many years of experience, our team ensures that every single transport is carried out reliably and safely – in the service of tomorrow’s sustainable energy supply.

DIMENSION CARGO

1 Transformer: 11,10 m x 3,68 m x 4,41 m, 280 t (LxBxH)

OVERALL TRANSPORT DIMENSION

Max. 87,5 m x 4,65 m x 5,60 m, 610 t (LxBxH)

VEHICLE TECHNOLOGY USES

  • Max. 2x 20 THP axles combined with side girder bridge G² | K600, a total of 4x reconfiguration of the vehicle combination and use of three different vehicle variants
  • Bridge overpass system
2024 BSK Award 1. Platz KS Transport_transparent

DEFYING DESPITE MISSING/DECAYING INFRASTRUCTURE

Due to irreparable damage to a transformer at the Dahlem substation, we were commissioned at short notice to transport the replacement transformer. As the infrastructure in the Dahlem area has been severely damaged by the flood disaster and some transport routes are no longer usable, our work to ensure supply security began already in nearby Kall. There, we took over the transport at a temporarily established rail-to-road transfer point and began the five-day journey from Kall to Dahlem (covering 30.6 transport kilometers).

Special Challenges:

  • Missing/decaying infrastructure
  • Reinforcement of a rail-to-road transfer point
  • Use of our bridge overpass system behind/in front of a 90-degree curve
  • Route with inclines of up to 8%
  • Very narrow clearance profiles
  • Three different vehicle combinations
  • 4x modification of the vehicle combination
  • Max. transport dimensions: 2x 20 THP axles, L 87.5 m x W 4.65 m x H 5.60 m, 610 t total weight

More

DIMENSION CARGO

1 Generator: 13,160 x 4,130 x 4,320 mm (L x W x H), 365 t

1 Transformer: 12,590 x 4,000 x 4,590 mm (L x W x H), 382 t

1 Flywheel: 8,070 x 3,350 x 2,900 mm (L x W x H), 182 t

OVERALL TRANSPORT DIMENSION

Generator: max. transport dimensions 31.25 m x 6.09 m x 6.00 m (L x W x H), 517 t

Transformer max. transport dimensions 31.25 m x 4.90 m x 5.80 m (L x W x H), 540 t

Transformer max. transport dimensions 50.00 m x 3.55 m x 4.25 m (L x W x H), 322 t

VEHICLE TECHNOLOGY USES

  • 18-axle SPMT (self-propelled modular transporter), 1.5-times coupled, 12-axle SPMT, parallel coupled, 18-axle THP (modular trailer), parallel coupled. Side girder bridge G² | K600, mounted on 2 x 16-axle THP modules
  • Deployment of Bridge Fly-Over Systems:
    1 fly-over system, 15 meters, 3 lanes
    1 fly-over system, 20 meters, 3 lanes
2024 BSK Award 3. Platz KJL Transport_transparent

SOPHISTICATED MULTIMODAL MEGA PROJECT

For the Würgassen substation, three heavy components – a 365-ton generator, a 182-ton flywheel, and a 382-ton power transformer – had to be transported from the manufacturers’ facilities to the southern Weser Uplands. Despite extremely short preparation times, we successfully asserted our transport concept against the competition and ensured the availability of all necessary equipment at all times. This allowed us to adhere to the specified project schedule, even in the face of highly fluctuating water levels on the Weser River.

Special Challenges:

  • Transport duration: 6 weeks
  • Strongly fluctuating water levels
  • Roll-off pontoon positioned across the main river flow (cross currents)
  • Use of a push boat
  • Very limited time window for planning and execution
  • Constraints due to curve radii and clearance profiles
  • Crossing of a railway line with a time window of approx. 2–3 hours
  • Driving simulations and tachymetric measurements
  • High safety requirements
  • A total of 5 different vehicle configurations
  • Simultaneous deployment of two bridge fly-over systems

More

DIMENSION CARGO

Generator: 9,76 m l x 4,15 m w x 4,32 m h , 350 to

OVERALL TRANSPORT DIMENSION

105 m l x 6,30 m w x 5,70 m h , 798 to

VEHICLE TECHNOLOGY USES

  • Use high girder bridge G² I K600
  • Various transport options, use hydraulic lifting gantries und fly over bridge
  • Permanent transport change from 2 x 26-axle high girder bridge G² I K600 to 2 x 16-axle high girder bridge G² I K600
  • Permanent double staffing required due to the transport process

 

2024 ESTA Award 1. Platz KJL Transport_transparent
2023 BSK Award 3. Platz KJL Transport_transparent

MULTIMODAL HEAVY TRANSPORT WITH A TOTAL WEIGHT OF 798 TONNES

A 350 tonnes generator from the Ibbenbüren power plant, which has already been shut down, is to be transported to the active Niederaussem power plant as a reserve generator. At the same time, the defective generator at the Niederaussem power station is to be moved to a different position.

Our task initially consisted of preparing the feasibility study and transporting both generators to Niederaussem and then positioning them within the power station.

After detailed CAD simulations, route tests, static calculations, method statements, risk assessments, etc. as well as multiple coordination meetings on site with representatives of the authorities and stakeholders, which took around 6 months, the transport could be realised.

The lack of generator end plates for this type of generator and the resulting overall dimensions of the transport variants made the project a particular challenge for man and machine.

More

DIMENSION CARGO

7 girder (pretressed concrete bridge)

per girder, 45,69 m l x 1,58 m w x 1,44 m h , 110 to

OVERALL TRANSPORT DIMENSIOM

61 m l x 3,00 m w x 4,25 m h , 199 to

VEHICLE TECHNOLOGY USES

  • 6-axle Trailer with 8-axle self-propelled trailers
  • 6-axle SPMT (Self-propelled modular transporter)

 

GERMANY’S LONGEST PRESTRESSED CONCRETE BRIDGE

Delivered safely and on time. Germany’s longest prefabricated prestressed concrete bridge. The special feature of the new record-breaking structure, the length of 45 metres. This innovative construction method means that the central pier can be dispensed with, which halves the overall construction time.
For this unique structure over the A1 near Ascheberg, we supplied a total of seven girders, each 45 metres long and weighing 110 tonnes each.
We are pleased to have been able to make our contribution to this record-breaking structure and to be working together on the modernisation of the German infrastructure.

DIMENSION CARGO

1 Transformer 1100 kV (World’s most powerful fransformer) 

13,35 m l x 6,14 m w x 5,87 m h , 535 tons

OVERALL TRANSPORT DIMENSION

64,30 m l x 7,45 m w x 6,45 m h , 875 tons

VEHICLE TECHNOLOGY USES

  • High Girder Bridge G² I K600 
  • Front: 2 power packs with 2 x 10 axle lines SPMT (Self-propelled modular transporter) parralel coupled
  • Back: 2 x 10 axle lines SPMT (Self-propelled modular transporter) parralel coupled
2018 Rekordtransport 1. Platz KS_transparent

RECORD TRANSPORT – TRANSPORT OF THE WORLD’S MOST POWERFUL TRANSFORMER

Already 12 months before the largest transformer ever built by Siemens – destined for China – started the first inner-city eight kilometres from the manufacturing plant to the port in Nuremberg, the specialists of the KAHL group of companies became active. The feasibility study commissioned by the customer required various route reconnaissance, elaborate measurements, carefully prepared official procedures and the assurance that suitable transport technology was available. For the enormous transformer with a transmission voltage of 1100 kV, and thus the world’s most powerful converter transformer, weighed in at 535 tonnes with a length of 13.35 m, a width of 6.14m and a height of 5.87m.

Based on load image and CAD simulations (EasyTrack, EasyLoad), the appropriate vehicle configuration was worked out in coordination with the engineering offices involved, which were commissioned with the static recalculations of the total of four bridge structures to be crossed.
Thanks to the innovative equipment of the KAHL group of companies, a vehicle combination could be provided which fulfilled all requirements for this record-breaking transport.

More

DIMENSION CARGO

1 home: 12 m l x 8,45 m w x 6,50 m h , 200 tons

OVERALL TRANSPORT DIMENSION

55 m l x 8,45 m w x 7,50 m h , 365 tons

VEHICLE TECHNOLOGY USES

  • 22-axle heavy-duty modules
  • 10-axle SPMT (Self-propelled modular transporter) 
2021 BSK Award 1. Platz KJL Montage_weiss

SIMPLY MOVE WHOLE HOUSES.

The challenge of the customer’s request was to lift a historic 65-year-old settlement house weighing 200 t (dimensions 12 m long, 8.45 m wide and 6.0 m high) from the basement foundation without distortion and in one piece and to move it from its location to the main road in the middle of a housing estate with different street levels, then to transport it over public roads and to place it on the newly constructed foundation at the destination without major interventions in the surroundings. Everything had to be done under the aspect of relocation, with the positioning at the new destination as true to the original as possible. The statics of the transport goods were particularly problematic because of its low stability due to a double wall with air chambers. 

More

DIMENSION CARGO

1 Turbine: 14,22 m l x 3,73 m w x 3,57 m h , 115 tons

OVERALL TRANSPORT DIMENSION

  • 1x 4-axle truck
  • 13-axle trailer

ANTONOV LOADING

Road, rail or waterways are usually available for the realisation of large-volume and heavy transports. But when things have to move particularly fast, there is fortunately another option – air freight. Since the 114-tonne turbine and its accessories were needed for an urgent overhaul and had to be delivered within a very narrow time window, there was only one solution – the Antonov An 124-100.

 

We took over the first section from the manufacturer to Cologne/Bonn Airport with our 13-axle modular chassis, which was pulled by a four-axle tractor. Arriving safely at the airport on schedule, one of the world’s largest aircraft for heavy loads – an Antonov An 124-100 of Volga-Dnepr Airlines – was waiting in the cargo area of the airport. The four-engine shoulder-wing aircraft with an impressive wingspan of over 73 metres was already waiting for its cargo with the nose flap up and the stowage system in place. With a crew of six, it can carry a maximum load of 120 tonnes, bringing its take-off weight to 392 tonnes. The turbine was loaded from our vehicle onto the Antonov’s loading ramp by a mobile crane with a maximum load of 500 tonnes. Pulled by steel cables, the turbine disappeared quite quickly into the large hollow belly of the machine. The load was securely fixed in a precisely defined position to prevent any movement during the flight. With so much weight in the belly, the fuel of the An 124-100 was initially sufficient to reach Athens. From there, after refuelling, it continued to its destination, the airport in Jeddah on the west coast of Saudi Arabia. With its cargo removed, the aircraft returned to Cologne/Bonn to pick up the turbine’s accessories.

DIMENSION CARGO

4 tranformers, each12 m l x 3,98 m w x 4,48 m h , 326 / 307 tons

OVERALL TRANSPORT DIMENSION

112,50 m l x 6,28 m w x 5,55/4,60  h, 742/ 766 tons

VEHICLE TECHNOLOGY USES

  • 2x 24 axle lines high girder bridge  G² I K600 
  • 1x 22 axle lines PST/SLE (SPMT/Self-propelled modular transporter)
  • Fly-over bridge system
2021 BSK Award 1. Platz KJL Transport_transparent

MULTIMODAL TRANSFORMER TRANSPORT

For the extension of the Würgau transformer station, 4 transformers with 326 + 307 t were transported multimodally from the transformer station in A-Weiz via the Danube port of Linz to the transformer station via the port of Bamberg. The pre-carriage was carried out by 32-axle Schnabel wagon (rail) to the heavy goods terminal in Linz, and then by inland waterway vessel to the port of Bamberg. For the unloading from the inland vessel and the subsequent loading into the 2 x 24-axle side girder bridge G² I K 600, we used a 900 t crawler crane. The task was not only to be able to carry the axle load of 12 t for the motorway bridges, but also the required clearance height for the good 4.5 metre high transformers! With a total train length of 112 metres, a width of 6.30 metres and a total train weight of 757 tonnes, it was possible to realise the required axle load of 12 tonnes on the structures by using another 10-axle running gear under the load. For the last part of the route to the transformer station, a reloading onto a 22-axle SPMT was necessary in order to cope with the 9% gradients with the serpentines.

More

DIMENSION CARGO

1 gas turbine: 12 m l x 3,98 m w x 4,48 m h , 338 tons

1 generator: 12 m l x 3,98 m w x 4,48 m h , 308 tons

1 transformer: 12 m l x 3,98 m w x 4,48 m h , 275 tons

VEHICLE TECHNOLOGY USES

  • 22-axle heavy-duty modules(3-file)
  • 6 trucks
  • 14-axle SPMT (Self-propelled modular transporter) 
2022 BSK Award 3. Platz PS Transport_weiss

FUTURE POWER SUPPLY SECURED

For the new construction of the gas-fired power plant Irsching 6, 3 plant components (gas turbine 338 tons, generator 308 tons and transformer 275 tons) had to be transported from the port of Kelheim to Voburg on the Danube.

The project included crane handling at the port, transport to the power plant, transhipment with mast and interim storage with SPMT, as well as subsequent internal transport with SPMT and foundation setting with mobile strand lifting system.

An entire logistics chain with crane, transport and assembly was required here. In addition to the special requirements due to the Corona pandemic (constant checks of all employees and special protection), the power plant operator also placed very high demands on occupational health and safety and environmental protection due to the immediate proximity to the Danube.

More

DIMENSION CARGO

1 generator: 3,60 m l x 3,25 m w x 3,00 m h , 40 tons

 TECHNOLOGY USES

  • Push and pull skidding system
  • 16 m long steel girders
  • Load distribution plates
  • 2 heavy-duty towers made of 8 elephant feet
  • Heavy duty platform
  • Working scaffold
  • Mobile crane
2022 BSK Award 2. Platz KJL Montage_weiss

DISASSEMBLY AND INSTALLATION OF A 40 to GENERATOR AT VW BAUNATAL

At the VW Baunatal power plant, a 40-tonne generator had failed and needed a general overhaul. We were commissioned with the removal (and later the installation) of the generator.
The special challenges of this installation work lay on the one hand in the insufficient load-bearing capacity of the floor area in front of the Geno, which only allowed 15 kN/m², and on the other hand in the actual removal from the building shell at a height of 9.20 m, only possible by dismantling the outer wall, up to the point of loading.
Due to complicated, time-consuming negotiations with external structural engineers and the customer about the unworkable concept presented by the customer’s structural engineering office, we ran out of time. In the end, our proposed solution prevailed.
With our own shifting track, the hydraulic lifting of the Geno, the substructure of 16m girders, various load distributors and the assembly of a steel construction, we moved the generator from its place to the outside and loaded it with a truck-mounted crane.

More

DIMENSION CARGO

1 phase shifter: 13.44 m l x 4.13 m w x 4.33 m h , 357 to

OVERALL TRANSPORT DIMENSION

60 m l x 6.40 m w x 6.40 m h, 684 tons

VEHICLE TECHNOLOGY USES

  • High girder bridge G² I K600 
  • 2 x 18 axle lines PST/SLE (SPMT/Self-propelled modular transporter) 
2022 BSK Award 2. Platz KJL Tranport_transparent

GENERATOR- TRANSPORT FOR SECURITY OF SUPPLY

The transport of a rotating phase shifter with a transport weight of 357 t from the Siemens Energy generator plant in Mülheim to Ludwigsburg-Hoheneck to the transformer station of the electricity grid operator Amprion, could only be carried out in a combined logistics chain with inland vessel, 650 t crawler crane for handling and the unique G² I K 600 boiler bridge, combined with 2×18-axle PSTE self-propelled units (SPMT) for the on-carriage.

After completion of the on-carriage, reloading onto a separate 18-axle self-propelled unit was required to bring it into the nacelle. We carried out the unloading with two masts in tandem lift. Extensive preparations, studies and calculations had to be taken into account in advance for the on-carriage from the port to the foundation.

More

DIMENSION CARGO

1 Stator: 14,68 m l x 4,20 m w x 4,50 m h , 400 to

VEHICLE TECHNOLOGY USES

  • High girder bridge G² I K600 
  • 2x 26-axle heavy-duty modules
  • 2x 14-axle heavy-duty modules
  • 2x 14-axle SPMT (Self-propelled modular transporter)
  • 2x 10-axle SPMT (Self-propelled modular transporter)
2019 BSK Award 1. Platz KJL Transport_weiss
2020 ESTA Award 1. Platz KJL Transport über 120t_weiss

BRAVURA PERFORMANCE IN FIVE VARIANTS

The generators of RWE’s Voerde power plant, which is currently being dismantled, are to be used as a strategic reserve for other locations. We had the task of taking over, removing and transporting the generators, each weighing 400 t, at a height of 13.4 m above the foundation and setting one of the generators down at the Neurath power plant.

This was preceded by almost a year of detailed preparation, including the preparation of CAD assembly and transport simulations, route tests, static calculations, method statements, risk assessments and coordination meetings with representatives of the authorities.

Challenges were the tight space conditions for the deployment in the nacelle, at the Nato ramp for RoRo loading and the restrictions with regard to axle loads and clearance profiles with vehicle dimensions of up to 105 m length x 4.68 m width and 5.70 m height and a total weight of 798 tonnes.

More

 

KAHL-Logo neu Claim negativ DE

KAHL Unternehmensgruppe
Pattbergstr. 33
47445 Moers-Repelen

KAHL-Logo neu Claim negativ DE

KAHL Unternehmensgruppe
Pattbergstr. 33
47445 Moers-Repelen

© 2025 KAHL SCHWERLAST GmbH | KAHL + JANSEN Schwerlast GmbH | KAHL & JANSEN GmbH International Logistics and Engineering | PIEPER Schwertransporte GmbH | KAHL & JANSEN Schwerlast-Montagen GmbH